Milestone sequence for QCH health service planning
| Action |
Completion Date
|
| Value stream planning groups confirm description models for the Project Definition Plan. Final PDP plan scheduled for completion in July 2008. The description modes for all services will be used as the basis of schematic design, where successive plans are produced and tested by working groups, consumers and staff to ensure the most efficient design of clinical and other spaces in QCH. |
Feb - July 2008 |
| QCH Health Service Plan released |
May/June 2008 |
| Project Definition Planning commenced using value stream structure outlined below |
January 2008 |
| Interim Health Services Plan produced incorporating feedback. Further refinement undertaken until the final plan available for release in first quarter of 2008. |
December 2007 |
| Comments period ends |
end October 2007 |
| Draft Comprehensive Health Services Plan issued for comment |
end September 2007 |
| Service Integration Groups convened & first meeting held |
31st March 2007 |
| Preparation of Comprehensive Health Services Plan commenced |
February 2007 |
| Initial Services Scoping Study completed |
February 2007 |
| Clinical SAGs convened & first meeting held |
27th February 2007 |
Details of QCH planning process are outlined below:
|
|
 |
|
 |