Milestone reporting
Milestones for the QCH project (most recent first)
2011 - 2010 - 2009 - 2008 - 2007 - 2006
2011
| August 2011 | Health Minister Geoff Wilson announces QUT and the University of Queensland as inaugural partners of the QCH Academic and Research Facility |
| July 2011 | The first sod is turned on the Leukaemia Foundation Queensland's new accommodation at Boggo Road Urban Village. Once the LFQ has moved to Boggo Road in early 2012, its current premises at South Brisbane will be demolished to clear the way for construction of the QCH Academic and Research Facility |
| May 2011 | Completion of level one slab floor of the QCH |
| March 2011 | Fiona Brewin-Brown appointed executive director of the QCH project |
2010
| November 2010 | Staff and students of the Mater Children's Hospital Special School celebrate the return of their new and improved playground |
| May 2010 | Pathology services are confirmed for the new QCH - a Queensland Government owned and operated pathology lab will provide vital pathology services to the new QCH |
| April 2010 | A fly-around of the new QCH is released First rudimentary room prototypes tested |
| March 2010 | Premier Anna Bligh, with the help of seven-year-old Jack Ford, turns the first sod on the QCH site |
| January 2010 | Abigroup is appointed as the QCH project's managing contractor |
2009
| December 2009 | Medical, nursing and allied health clinical leaders are appointed to help lead and manage the integration of the Royal Children's and Mater Children's hospitals into the QCH |
| November 2009 | Stage one of the Mater's Hancock Street car park opens |
| October 2009 | Another floor is added to the design of the QCH taking it from 10 to 11 levels |
| July 2009 | Commencement of the developed design phase |
|
January 2009 |
Dr Peter Steer is appointed CEO of Children's Health Services. This role includes responsibility for developing the services the QCH will deliver |
2008
| November 2008 | Second feedback convention involving clinician and family /community members to refine the Schematic Design |
| September 2008 | Commencement of the Hancock Street Carpark (a Mater Health Services Project). The car park is a necessary first step to deliver the QCH project |
| September/Oct 2008 | Master Plan for QCH and the Preliminary Business Case approved by Cabinet Budget Review Committee |
| June 2008 | Commencement of Schematic Design phase of planning. This involves some 40 core and sub groups in detailed planning of proposed clinical and other spaces. Feedback process from the groups and several planned conventions will progressively refine the design to meet the needs of how services will be delivered in the QCH |
| End June 2008 | Project Definition Plan completed - a stage required to inform the progressive stages of Schematic Design |
| 12 June 2008 | The Queensland Paediatric Cardiac Service officially opened by the Minister for Health at the Mater Children's Hospital |
| End May/early June 2008 | Release of Queensland Children's Hospital Health Service Plan 2008-2018 |
| 20 May 2008 | Patients transfer from The Prince Charles Hospital Queensland Paediatric Cardiac Service (QPCS) to Mater Children's Hospital |
| End March 2008 | Finalisation of Master Plan report |
| 15 March 2008 | Family Forum held at Mater Children's Hospital to introduce Queensland Paediatric Cardiac Service cardiac families to new facilities |
|
Feb 2008 |
First outpatient clinic conducted at Mater Children's Hospital in advance of the move of Queensland Paediatric Cardiac Service from The Prince Charles Hospital to the Mater campus |
2007
| 1 October 2007 | Paediatric cancer patients transfer from Mater Children's Hospital to Royal Children's Hospital as part of service planning leading to the establishment of the QCH |
| Sep/Oct 2007 | QCH Draft Health Service Plan available for staff and community consultation |
| 21 August 2007 |
First meeting of QCH Project Delivery Committee |
| July/Aug 2007 | Appointment of QCH project consultants |
| June 2007 | First meeting of QCH Youth Advisory Forum |
| 31 May 2007 |
First meeting of Joint Hospitals Executive |
| 19 April 2007 | QCH website goes live |
| 18 April 2007 | First meeting of Family Advisory Council at Parliament House |
| 13 April 2007 | Future of general paediatrics at QCH Workshop |
| 26 March 2007 | Visioning and Regional Service Planning Workshop - Cairns |
| 19 March 2007 | Research Workshop |
| 15 March 2007 | Inaugural Statewide Regional Services Workshop |
| 23 February 2007 | Third Visioning Workshop for QCH |
| 2 February 2007 | Second Visioning Workshop for QCH |
| 21 February 2007 | Queensland Paediatric Cardiac Service Transition Workshop |
2006
| 28 November 2006 | Initial Visioning Workshop for QCH |
| 17 October 2006 | Initial meeting of the Strategic Advisory Committee |
| 11 September 2006 | Appointment of Professor Alan Isles as Clinical CEO |
| 27 August 2006 | Government announces election commitment to building Queensland Children's Hospital |