Project Milestones

October 2006 Community Reference Group (CRG) formed and meetings commenced
March - April 2007 Contracts were awarded to private, independent companies to undertake various studies for the Health Impact Assessment (HIA)
May 2007 Tender awarded to conduct the community health survey
May - September 2007 Environmental monitoring commenced
September 2007 Community survey undertaken on a sample of local residents
November 2007 Environmental monitoring continued
January 2008 Health risk assessment and Post event review commenced
April 2008 Environmental monitoring continued
June - July 2008 Post event review of two chemical fires (Binary Industries and Zelam Australasia) to be completed
July - October 2008 Emission scoping undertaken
December 2008 - May 2009 Monitoring postponed due to wet weather conditions
May - June 2009 Emissions monitoring conducted
August - January 2010 Emissions modelling
January - March 2010 Health risk assessment
May 2011 Health Impact Assessment Narangba Industrial Estate May 2011 completed
May 2011 Government Agency Progress Report - Response to Recommendations completed