Sunshine Coast University Hospital construction timetable
Timeframe Milestone
September 2012 - end 2013 Design development process
October 2012 Site establishment and bulk earthworks commence
February 2013 - December 2013 First multi-deck car park
June 2013 - December 2013 Kawana Way duplication works
Mid-2013 - end 2014 Main hospital structure
Early 2014 - mid-2015 External facade
From mid-2014 Internal fit-out and finishes
April 2017 Public hospital opens with about (450 beds)
2021 Public hospital fully commissioned

Last updated: 8 March 2016