Public consultation
Community engagement was undertaken as part of the Ministerial Infrastructure Designation (MID) process for each site. The MID process provides an alternative to lodging a development application with the relevant local government and is managed by the department with input from other government agencies.
Two phases of community engagement were undertaken:
- Phase one: Preliminary engagement (for 10-15 days) with targeted key stakeholder groups.
- Phase two: Formal public notification and engagement (for 20 days) with the broader community and interested stakeholder groups.
Feedback from both consultation phases informed the MIDs lodged with the Minister for State Development, Infrastructure, Local Government and Planning.
Please visit the Ministerial Infrastructure Designations public register for more information about the Satellite Hospital decisions and gazettals.
- MID-0921-0528 - Bribie Island Health Care Facility
- MID-0821-0519 - Caboolture Health Care Facility
- MID-0622-0607 – Eight Mile Plains Health Care Facility
- MID-1021-0539 - Kallangur Health Care Facility
- MID-0821-0520 - Redlands Health Care Facility
- MID-0821-0518 - Ripley Health Care Facility
- MID-1021-0536 - Tugun Health Care Facility
Bribie Island Satellite Hospital
The Bribie Island Satellite Hospital site was announced in June 2021. The site is approximately 6.1 hectares and is located at 65-101 First Avenue, Bongaree QLD 4507.
Project timeline
Phase | Timing |
---|---|
Preliminary engagement phase MID | August 2021 |
Formal public engagement phase MID | September to October 2021 |
MID process complete | November 2021 |
Construction phase | 2022 — 2024 |
Caboolture Satellite Hospital
The Caboolture Satellite Hospital site was announced in June 2021. The site is approximately 1.5 hectares and is located at 15 Rowe Street, Caboolture QLD 4510.
Project timeline
Phase | Timing |
---|---|
Preliminary engagement phase MID | August 2021 |
Formal public engagement phase MID | October 2021 |
MID process complete | November 2021 |
Construction phase | 2022 – 2023 |
Eight Mile Plains Satellite Hospital
The Eight Mile Plains Satellite Hospital site was announced in June 2022. The site is approximately 1.5 hectares and is located at 59 Levington Road, Eight Mile Plains QLD 4113.
Project timeline
Phase | Timing |
---|---|
Preliminary engagement phase MID | February 2022 |
Formal public engagement phase MID | April 2022 |
MID process complete | June 2022 |
Construction phase | 2022 – 2024 |
Kallangur Satellite Hospital
The Kallangur Satellite Hospital site was announced in June 2021. The site is approximately 1.5 hectares and is located at 159-163 Dohles Rocks Road, Kallangur QLD 4503. This is within the Mill Priority Development Area (PDA).
Project timeline
Phase | Timing |
---|---|
Preliminary engagement phase MID | September 2021 |
Formal public engagement phase MID | November 2021 |
MID process complete | December 2021 |
Construction phase | 2022 – 2023 |
Redlands Satellite Hospital
The Redlands Satellite Hospital site was announced in June 2021. The site is approximately 1.4 hectares and is located at 22-28 Meissner Street, Redland Bay QLD 4165. This is within the Weinam Creek Priority Development Area (PDA).
Project timeline
Phase | Timing |
---|---|
Preliminary engagement phase MID | August 2021 |
Formal public engagement phase MID | October 2021 |
MID process complete | November 2021 |
Construction phase | 2022 – 2023 |
Ripley Satellite Hospital
The Ripley Satellite Hospital site was announced in June 2021. The site is approximately 2.7 hectares and is located at 150 Botany Drive, South Ripley QLD 4306. This is within the Ripley Priority Development Area (PDA) and is earmarked as a health-related precinct within the Ripley Valley Master Plan.
Project timeline
Phase | Timing |
---|---|
Preliminary engagement phase MID | August 2021 |
Formal public engagement phase MID | September to October 2021 |
MID process complete | November 2021 |
Construction phase | 2022 – 2023 |
Download information about the preliminary and formal public notification phases for the MID:
- Formal public consultation - Ripley satellite hospital concept design (PDF 3285 kB) (indicative only)
- Formal public consultation - Ripley satellite hospital proposed site location and concept floor plan (PDF 3022 kB) (indicative only)
- Newsletter - Ripley satellite hospital public consultation newsletter - September 2021 (PDF 2056 kB)
- Preliminary consultation - Ripley satellite hospital concept design (PDF 9582 kB) (indicative only)
- Preliminary consultation - proposed Ripley satellite hospital site layout (PDF 1273 kB) (indicative only)
- Preliminary consultation - Ripley satellite hospital site location aerial view (PDF 2629 kB) (indicative only)
Tugun Satellite Hospital
The Tugun Satellite Hospital site was announced in June 2021. The site is approximately 1.4 hectares and is located at 57 Boyd Street, Tugun QLD 4224.
Project timeline
Phase | Timing |
---|---|
Preliminary engagement phase MID | September 2021 |
Formal public engagement phase MID | October to November 2021 |
MID process complete | December 2021 |
Construction phase | 2022 – 2023 |